Paving Update – November 4, 2025
The Town’s paving contractor completed surface milling today. Tomorrow and Thursday (November 5 and 6), the contractor is scheduled to make extensive repairs to the road base in the 3900 block of Woodbine Street, which was found to be in bad disrepair. The contractor will also do some prep work on Leland Street to in advance of final resurfacing, to be done when all of the base repairs are made.
Please contact the Town Office if you have any questions. Thank you.