Permit ProcessFollowing is a sequential overview of the Town's building permit and inspection process. The Town's Community Relations Committee also has prepared a brochure entitled "Ten Things to Know Before Renovating or Building in the Town of Chevy Chase." Additionally, a flow-chart detailing the Town's permit review process can be found here.
Pre-Permit Application Consultation (Pre-PAC):
Prior to filing a building permit application for a new building in excess of 500 square feet or for one or more addition(s) or alteration(s) that individually or cumulatively increases the square footage of any floor of an existing building by more than 500 square feet, the Town requires a consultation with Town officials for purposes of exchanging information, receiving feedback, and making and considering non-binding recommendations. All persons subject to such a consultation shall file, with the Town Manager, a preliminary plan including at least the following:
Ten days prior to the Pre-PAC meeting, the Town will post information about the meeting on the applicant's property and on the Town website. The Town also will send a notice of the consultation to abutting and confronting neighbors.
Permit Application:
A town building permit application may be filed at any time following a Pre-PAC, if required; however, no town building permit shall be issued unless and until a County building permit for the same work has been issued and the applicant has held a site management meeting (see below), if required. The submittal requirements below apply only to New Construction, Addition, Demolition, Wall, Deck, Porch, Patio (over 700 s.f.), and Non-Vegetative Front Yard Surface Permits
Submittal Requirements:
Permit Review:
Once the Town has received a complete building permit application, the Town staff performs a thorough evaluation of each element of the permit, including the construction plans, the tree protection plan and the water drainage and tree removal plans, if applicable. If any element of a building permit application does not meet Town development standards, the Town staff will notify the applicant to discuss how to bring the application into compliance with the Code.
Site Management Meeting:
Prior to issuing a building permit for a new building in excess of 500 square feet or for one or more addition(s) or alteration(s) that individually or cumulatively increases the square footage of any floor of an existing building by more than 500 square feet, the Town requires a mandatory consultation with Town officials for purposes of discussing site management issues and assisting the Town Manager in establishing site management conditions to protect the public health, safety and welfare. Site management conditions that may be imposed include, but are not limited to:
Ten days prior to the site management meeting, the Town will post information about the meeting on the applicant's property and on the Town website. The Town also will send a notice of the consultation to abutting and confronting neighbors.
Permit Issuance: The permit will be issued in the name of the property owner who may authorize, in writing, an agent to represent the owner in connection with the application and any permit issued by the Town Manager. Once the permit has been issued, it is unlawful to modify or alter any plans or specifications without the prior approval in writing of the Town Manager. Work must be commenced within six (6) months of date the permit is issued and must be completed not later than twelve (12) months from date the permit is issued, or the permit shall be void, unless an extension is granted in writing by the manager.
Inspections: During the course of construction, Town officials are involved in four inspections that are performed at the same intervals as those required by the Montgomery County Department of Permitting Services. All inspections shall be requested 48 hours prior to the date the inspection is needed. A set of approved plans stamped by the Montgomery County Department of Permitting Services must be available for the inspector's review.
|
||
![]() |
|||
| Site Map | Privacy Policy | Website Usage Terms & Conditions © Copyright 2005, The Town of Chevy Chase Website Design by Calvert Design Group |
|||